Decision to withdraw
Microsoft has withdrawn from an AI data center project planned by Nscale in Loughton, Essex, UK, with a £2 billion investment. According to the BBC, the company was to finance a supercomputer at the facility.
Microsoft did not comment on the matter. Nscale announced that it will continue with its plan to build the project.
Power connection delay
The data center's power connection was planned to be provided by the end of 2026. However, Nscale was told that the connection could be delayed until the 2030s. The delay, first reported by The Telegraph, shows that AI data centers are constrained not only by investment but also by power infrastructure.