What was announced
Meta said it has completed the first phase of its gigawatt-scale Prometheus supercluster at its New Albany, Ohio data center. According to the company, this capacity was used to train its new Muse foundation models.
Prometheus currently spans hundreds of thousands of GPUs across multiple buildings. The site is designed to function as a single machine, linked by miles of fiber. Meta aims to reach roughly 1 million GPUs at full scale.
Hardware and cooling
The supercluster currently uses two NVIDIA GPU platforms, with a third based on NVIDIA's Vera Rubin NVL72 arriving soon. The first platform, Catalina, uses the Ariel variant of GB200 NVL72, a two-rack configuration that links 72 GPUs into a single accelerator domain.