What happened
SemiAnalysis researchers who visited the site in September reported that the first 120 MW of the Galaxy data center campus in Ulanqab, Inner Mongolia, was completed in under a year. The report puts the cost at roughly one-fifth of comparable US projects.
The campus is being developed in four phases for two unnamed internet companies. Once complete, it is planned to offer up to 800 MW of IT capacity by the end of 2027, close to the roughly 820 MW at the Stargate campus in Abilene, Texas.
Power from its own farms
Rather than relying on the local grid, Envision is building its own generation. It is installing wind farms about 80 kilometers apart with a combined capacity of 420 MW, intended to supply more than 60% of the electricity for the campus's first two phases. Four-hour battery storage is being added to cover periods when the wind drops.